Introduction
Project Type
Solar Park
Owner
Federal Electricity Commission (CFE)
Location
Puerto Peñasco, Sonora, Mexico
CO2 Prevented
About 280,569 tons average annual
Installed Capacity
153MW
Power Generation
348,534 MWh average annual
Module Type
ASTRO 5 (545W)
Grid-Connected Time
April, 2023
Case Highlights
Mexico Puerto Penasco 153MW Solar Park, constructed by CHINT Solar Mexico, is equipped with 288,757 ASTRO 5 modules with a unit capacity of 545W, which is expected to avoid approximately 280,569 tones of CO₂ annually.
During the construction, the project was urgent and must meet all requirements and dates, including challenges during the pandemic, Astronergy ensured the efficient and high-quality completion of module supply. Full capacity of modules arrived in seven deliveries, each delivery with approximately 21 MW, which means 65 containers per week.